Roundabout
Roundabout Construction Update: Week of February 6, 2023
Important Closure Update
Portions of Pacific Street and Rocklin Road will be closed during normal working hours of 7 a.m. to 5 p.m. for utility adjustment. Detours will be in place prior to these closures. At the end of the work shift on Monday, these closures will be re-opened to traffic until Tuesday morning. Crews will then set the detours and closures again on Tuesday to patch pave the newly adjusted utilities.
This will not be a complete closure; limited traffic will be allowed to move through the roundabout.
Rocklin Rd. and Pacific St. Roundabout Frequently Asked Questions
1. What is the total projected cost of the project and how is it funded?
The project is 100% funded by the Congestion Mitigation and Air Quality (CMAQ) Federal Grant, awarded to construction contractor George Reed for$4.46 million. No local funds are being used.
2. When will construction be complete?
The contractor has 180 working days to complete the project. With the official start on April 18, 2022, the project is scheduled to be completed by Jan. 5, 2023.
Video: Business Stakeholder Meeting Summary
The Rocklin Road and Pacific Street roundabout project team hosted a virtual meeting on Sept. 29 to provide business stakeholders information about construction, which is scheduled to begin this fall, and answer logistical questions about the project.